Deck bearers
Stage 6
The Deck Bearers were brought in at high level from the now completed abutment on the north bank, probably having been cast in a temporary furnace in The Square next to the Bridge. Each one was different and made to measure. Each pair of straight Deck Bearers was linked at the centre by a 5m long curved casting, the Crown Bearer, which gripped and tightened the Crown Joint. All the joints on the Bridge were then packed with iron blocks and wedges, which were sealed in with lead.
Stage 7

Stage 7: The cast iron deck plates and their locating wedges were revealed in 1975 while laying a new road surface. ©