Weymouth's harbour repair work begins

Work on Weymouth harbour wall The work on Weymouth Harbour is due to be completed by June 2013

Related Stories

Work has begun on a £4m scheme to repair a harbour in Dorset.

Contractors are rebuilding a ferry berth in Weymouth where deep cracks beneath the waterline have led to parts of the harbour wall collapsing.

Condor Ferries, which sails from Dorset to the Channel Islands, is currently leaving from Poole because the Weymouth berth is out of action.

The 80-year-old berth was declared unsafe in February and remedial works proved unsuccessful.

The work is expected to be completed by June 2013, with the ferry company hoping to move back the following month.

The instability is thought to have be down to a phenomenon called scour, caused by natural processes such as tides, currents and changes in the seabed, as well as by boats and other harbour uses.

More on This Story

Related Stories

The BBC is not responsible for the content of external Internet sites

BBC Dorset

Weather

Bournemouth

Min. Night 14 °C

Features & Analysis

Elsewhere on the BBC

  • MoviesMovie magic

    Tech that reads your desires is helping to increase your odds of producing a hit film, says BBC Future

Programmes

  • Ade Adepitan at the ColosseumThe Travel Show Watch

    The challenge of providing disabled access at Europe’s leading ancient monuments

BBC © 2014 The BBC is not responsible for the content of external sites. Read more.

This page is best viewed in an up-to-date web browser with style sheets (CSS) enabled. While you will be able to view the content of this page in your current browser, you will not be able to get the full visual experience. Please consider upgrading your browser software or enabling style sheets (CSS) if you are able to do so.